Wednesday, March 14, 2012

Dredge Update

A reader asked about the dredging operations underway on the Madison County side of the lake.  We passed the request on to Greg Burgess, Chief Engineer for the Pearl River Valley Water Supply District.  Greg provided the following response.

We have completed the portion of the dredging between Overlook and Point Clear. We are now dredging the other part of this project which is between Overlook and Old Trace Park. We do not want this project to be in the way this boating season and are making all efforts to complete this section as quickly as possible. We are scheduled to complete this project, including the removal of the piping from this area, by May of this year. 

The Rez News
Barnett Reservoir

No comments: